Project Update: Significant Progress Moving into Fall
Hello, Fall!
As we welcome fall slowly (I don’t mind this lingering sun!), we will not only see the trees change color and the landscapes begin to change, but we’ll also see some significant progress on the building site.
Looking Ahead
Rimmer & Roeter continues to work on the steel stud framing. The Iron Erectors have arrived this week and are familiarizing themselves with steel pieces and preparing their plan. We expect to see the Iron Erector crew increase by mid-October, with an additional team arriving in about three weeks. Towards the end of October, the concrete deck slab is expected to be poured. Exciting things are happening in the next few months. Stay tuned and watch while the site and leaves begin to change around us!